Posted by Suzanna Hinson

Whilst many European reactors are hampered with delays, construction of four new units in the United Arab Emirates (UAE) is on or even ahead of schedule. The Emirates Nuclear Energy Corporation (ENEC) announced that the Barakah Nuclear Energy plant is now 75% complete and still scheduled to finish in 2020.

The first of four APR – 1400 PWR units is expected to start operation this year, with the others coming online each consecutive year afterwards until the entire plant is generating in 2020. Unit 3 recently passed the milestone of having its reactor containment linear dome installed and Unit 4 is ahead of schedule with the concrete for the containment building now being poured. The plant is being built by a South Korean-led consortium with close consultation from the International Atomic Energy Agency and huge public support.

Surveys conducted by ENEC show that public support has increased with the construction of the plant. In December 2012, 82% of people surveyed were in favour of nuclear energy compared to 66% in 2011. An even greater figure of 89% of those surveyed supported a plant being built in the UAE, up from 67% in 2011, before construction started. The 2012 survey also found that awareness of nuclear energy had increased with a total of 89% believing that peaceful nuclear energy is “extremely important,” “very important,” or “important” for the UAE.

The power plant, which began construction in 2012, will provide when completed up to a quarter of the UAE’s electricity demand (5600MWe) and in doing so, save up to 12 million tonnes of carbon emissions per year. 

Leave a Reply

Sign up for our Weinberg Next Nuclear Newsletter
* = required field

The Alvin Weinberg Foundation’s work has helped us to understand the potential benefits of thorium and next generation nuclear reactors, such as the Molten Salt Reactor.

— All-Party Parliamentary Group on Thorium Energy

@thorium_wf

Our latest blog on the nuclear report from the Science and Technology Committee of the House of Lords. We need... https://t.co/CPqKOPpyOg
- Wednesday May 3 - 2:36pm

Recent Posts

Three Mile Island – the real disaster

by Suzanna Hinson (June 2nd, 2017)

Nuclear in Africa

by Suzanna Hinson (May 16th, 2017)

Engineers echo politicians: SMRs could help the UK post-Brexit

by Suzanna Hinson (May 11th, 2017)

Breaking the cycle of indecision: nuclear report by the House of Lords

by Suzanna Hinson (May 3rd, 2017)

Posts Archive

Categories

  • Economics (89)
  • Efficiency (54)
  • Policy (17)
  • Proliferation (32)
  • Regulation (8)
  • Safety (63)
  • Security (18)
  • Technology advances (23)
  • Uncategorized (53)
  • Waste (52)
  • © The Alvin Weinberg Foundation 2014
    The Alvin Weinberg Foundation is a registered UK charity. Charity number: 1155255
    The Alvin Weinberg Foundation web site uses cookies to record visitor patterns.
    Read our data protection policy

    Design by Tauri-tec Ltd and the Alvin Weinberg Foundation